Status as of April 12, 2022
Collins Road, U.S. 80 to Tripp Road

Roadway construction is complete. Light pole installation will be done as soon as possible. The Town is investigating possible upcoming landscape improvements in the medians of the roadway.
Collins Road, Tripp Road to Town East Boulevard

Design is underway on this project. The Town is hoping to have preliminary drawings complete this summer, at which time we will schedule a meeting for the public to view the plans and ask questions.
Collins Road (SH 352), U.S. 80 to Mesquite City Limits

This project is under construction and is being managed by the Texas Department of Transportation (TxDOT). The project should be completed later this year.
Tripp Road Culvert Replacement

This project is under construction with an estimated completion time at the end of April 2022.
Jobson Road Wetlands Bypass (Jobson Road at Stoney Creek Boulevard)

This project is under construction with an estimated completion time at the end of April 2022.
Barnes Bridge Road crossing over Duck Creek

The bridge remains closed to traffic. The Town entered into an agreement with TxDOT for them to do all design and replacement work for the bridge. TxDOT will also pay 90% of the project cost. The bridge replacement is on TxDOT's schedule and is anticipated to be complete in 2025.
Harris Addition Sewer and Alley Replacement,
Phase 1

This project is substantially complete although the contractor is addressing clean-up issues. The Town is hoping to have a final walk-through on this project later this month.
Harris Addition Sewer and Alley Replacement,
Phase 2

This project is in the early stages of design. The Town hopes to start the bidding process for this work before the end of 2022.
Drainage improvements on Tripp and Jobson Roads, near the Harris Addition

This project is in design. Construction will be scheduled around other projects in the area in an effort to minimize disruption.
Tripp Road drainage improvements, east of Collins Road

Design on this project is substantially complete. The Town is starting the process of acquisition of required right-of-way and easements. After this is complete, the project will be sent out for bids, hopefully before the end of the year.
2022 asphalt road repairs (various locations)

Map (PDF)

Work is underway to do repair/replacement of pavement on multiple roadways within the Town, including Collins Road, Town East Boulevard, Long Creek Road, and others. This work should be completed in late spring or early summer. Staff is also preparing bid packages for additional roadway sections within the Town.